Mimosa Acres Drainage Improvements

Print
Press Enter to show all options, press Tab go to next option

Project Overview

About. The project area, located in Mimosa Acres Subdivision, is bound by Cherry Street, Francis Drive, W. Pear Street and Woody Drive. The purpose of this project is to address the repetitive loss during inclement weather despite being located outside of the FEMA mapped flood hazard zone.  Improvements are intended to reduce the nuisance of both street and structural flooding by addressing problems attributed to undersized culverts, storm sewer, as well as minimal maintenance of the drainage system. This was an area identified in the Harvey Drainage Assessment Report as a local drainage improvement project.

Scope:  Drainage improvements for the subdivision will require removal/ replacement of driveways, driveway culverts, storm sewer system, and re-grading of the ditches to return grades to the original design capacities. The project will also include an asphalt overlay of the road to repair damage due to the drainage improvements. 

Residents can also register to reveive project updates through the City’s e-notification system Everbridge.  Project information is often available through the City’s FaceBook page, Twitter and Instagram accounts as well.  We encourage residents and property owners’ to sign up for the e-alerts and information, please contact Fatema Weekly, Project Manager, at fweekly@pearlandtx.gov

This project is part of the 2019 Bond referendum. 

Schedule Info 

Design schedules vary per project. Typical Bid schedules run approximately 60 days to advertise, hold pre-bid meeting, respond to any bidder questions and open bids. Under normal circumstances, without irregularities, a bid can be awarded within 24 days of the Bid Date. This could extend another 14 days if there are questions regarding the Bidder’s qualifications. A construction Notice to Proceed is generally issued with 10 to 14 days of Award bringing the total process to about 90 days from Advertisement to Notice to Proceed.

Base Line Current
Design Start July 2019 August 2020
Bid Start May 2020 June 2020
Construction Start August 2020
Proposed Construction Completion March 2021

 
 

Budget and Funding Info
2019

 Project Area 

Mimosa Acres map